We were entrusted by Dorset Council to install two new classrooms and a toilet bock as a single modular building. From installing the foundations to handing the keys over this project was completed over the 6 weeks summer holidays.
Including the travelling from the cranes base in Germany, the lifting installation was completed over a three-day period.
Preparation for crane
Trackway and crane setting up
Modular units arriving
Lifting of the modular units
Lifting installation complete
If you would like a no-obligation quote please contact the office at 01305 813318 to discuss your extension or building project with our team at David R White Building Services Ltd.